Mill Springs, North Carolina · 2024
Pure Country Weavers
A 264 kW fully-ballasted rooftop PV array for Pure Country Weavers in Mill Springs, NC — no mechanical anchors, completed three weeks ahead of schedule on a TPO roof.
System size
264 kW-DC
Completed
2024
- Location
- Mill Springs, North Carolina
- Modules
- 527 × PS-M144(HCBF)
- Mounting system
- FastRack 510-6dg at 10° tilt
- Mount type
- Rooftop
- Structural method
- Fully ballasted — no mechanical anchors
Why this project worked
- 480 FastRacks supporting 527 modules for a 264 kW system
- Fully ballasted with zero mechanical anchors
- Completed three weeks ahead of schedule
- Installer's first ballasted system — successful enough to want another
Overview
Pure Country Weavers is a textile manufacturer located in Mill Springs, North Carolina. Framed by the iconic Blue Ridge Mountains, this rooftop build offsets 264 kW. The array is fully ballasted and required no mechanical anchors. Sollega provided the photovoltaic system and 480 FastRacks for 527 modules.